The re-roofing project on the William Henry Harrison High School in West Lafayette, Indiana involved the steep-slope roof areas totaling approximately 15,000 square feet.
Project Overview

Owner:  Tippecanoe School Corporation

Location:  West Lafayette, Indiana

Lead Consultant:  Greggory H. Nichols, RRC, RRO

STR-SEG Design Team:  Randy Marquardt

Project Budget: $250,000.00

 

Details of Project Successes/Challenges:

The re-roofing project on the William Henry Harrison High School in West Lafayette, Indiana involved the steep-slope roof areas totaling approximately 15,000 square feet. The existing metal panel finish had deteriorated and surface rusting was occurring at the seams. The new roof system features 4-inches of rigid insulation, a 1/2-inch plywood and synthetic underlayment followed by the installation of a distinctive 24 gauge prefinished galvanized architectural standing seam metal roof.